The Executive Committee, having considered the comments and recommendations of the Sub-Committee on Monitoring, Evaluation and Finance (UNEP/OzL.Pro/ExCom/28/4, paras. 3 and 4), decided:*
(a) To reaffirm decision 22/38 on equipment destruction and decide that, in order to clarify the issue of phase-out claimed as a result of projects“completed”, the following language should be added to the definition of“completed project” contained in decisions 17/22 and 19/23:“that no further use of CFCs is in evidence, that the alternative product is being produced and/or production has begun, and that the CFC-using equipment has been destroyed/dismantled/ rendered unusable with CFCs”;
(b) That formal agreements should be concluded among the national government, the enterprise and the implementing agency requiring that replaced equipment should be destroyed/dismantled/rendered unusable and that no CFCs should be used after completion of projects.
*As per decision 30/6, the Executive Committee decided to add the following paragraph to Executive Committee decision 28/2: "To request the agencies to withhold, wherever possible, part of the project funding or reimbursement of cost until proof of disposal and destruction of equipment has been provided."