Decision 32/3

December 2000
UNDP | UNEP | UNIDO | World Bank
Report on balances and availability of resources

Taking note of the report on completed projects with balances (UNEP/OzL.Pro/ExCom/32/6) and having considered the recommendation of the Sub-Committee on Monitoring, Evaluation and Finance (UNEP/OzL.Pro/ExCom/32/3, para. 9), the Executive Committee decided:

(a) To take note of the return at the 32nd meeting of US $2,977,982 from UNDP, US $46,400 from UNEP, US $330,901 from UNIDO, and US $994,997 from the World Bank;

(b) To note that UNIDO and UNDP plan to return balances from completed projects to the Fund at the 33rd meeting of the Executive Committee;

(c) That balances from completed recurring projects should be returned to the Fund for reprogramming;

(d) To request the Secretariat and UNDP to resolve the data discrepancy of US $77,315 contained in the report submitted by UNDP on completed projects with balances by the 33rd meeting of the Executive Committee.