China: 2001 Annual programme - Halon sector (World Bank) (UNEP/OzL.Pro/ExCom/32/30/China)
Having considered the recommendations of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/32/21, para. 84), the Executive Committee decided:
(a) To approve the above project at the level of funding indicated in Annex VIII to the present report (the independent technical audit is included in the 10 per cent agency support cost);
(b) To request that future technical audits required under the agreement be submitted by the World Bank no later than eight weeks prior to the meeting of the Executive Committee at which approval of funding was being sought.