Following a discussion on the requests for changes in due dates, the Executive Committee decided:
- To note the information on annual tranches of multi-year agreements (MYAs) submitted to the Secretariat by Germany, UNDP, UNIDO, and the World Bank as contained in the document on annual tranche submission delays (UNEP/OzL.Pro/ExCom/49/17);
- To agree to the changes in due dates for specific annual tranches as indicated in the following table:
| Country | Agency | Project Title | Tranches | Proposed Change | Reason for Change | 49th Meeting Submission |
| Bangladesh | UNDP | National ODS phase-out plan | 2007 due in 2007 | Second Meeting | To accommodate time required to complete performance verification of the previous year. | Request for the release of all tranches at the 52nd Meeting. |
| Bangladesh | UNEP | National ODS phase-out plan | 2007 due in 2007 | Second Meeting | To accommodate time required to complete performance verification of the previous year. | Request for the release of all tranches at the 52nd Meeting. |
| Lebanon | UNDP | National phase-out management plan for Annex A– Group I substances (CFCs) | 2007 due in 2007 | Second Meeting | To accommodate time required to complete performance verification of the previous year. | Letter received. |
| Mauritius | Germany | Implementation of an ODS terminal phase-out management plan | 2005 | Third Meeting | Lack of necessary funds for next tranche. | Germany indicated that the words in the letter from the Government, "later in 2006", meant the third meeting of the year. |
| Lesotho | Germany | Terminal CFC phase-out management plan | 2005 | Third Meeting | Lack of necessary funds for next tranche. | Germany indicated that the words in the letter from the Government, "later in 2006", meant the third meeting of the year. |
- To note that 13 of the 17 annual tranches of MYAs that were due for submission were submitted on time to the 49th Meeting; and
- To note that letters should be sent to implementing agencies and the relevant Article 5 Governments for the following annual tranches due for submission to the 49th Meeting but not submitted for the reasons indicated below and to encourage them to submit these annual tranches to the 50th Meeting:
| Country | Agency | Project Title | Annual Tranche | Reason for Delay |
| Kenya | Germany | Technology transfer leading to methyl bromide phase-out in soil fumigation in all other horticulture | 2006 | Need to submit along with the companion UNDP project. |
| Libyan Arab Jamahiriya | UNIDO | National phase-out plan | 2006 | Pending verification report. |
| The Former Yugoslav Republic of Macedonia | UNIDO | Terminal phase-out management plan for CFCs | 2006 | Pending verification report. |