Decision 50/35

November 2006
China
World Bank
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To take note of the maximum allowable CTC production and imports for controlled use as process agents under both phases I and II in China, and as feedstock for CFC production for 2006 at 28,618 ODP tonnes;
  2. To amend the maximum allowed CTC production for consumption under the Montreal Protocol in row 1 of Appendix 2-A to the phase II Agreement as follows:

Maximum allowed CTC production for

consumption under the Montreal Protocol

Baseline (2003)20062007200820092010
 29,3677,341.77,341.77,341.77,341.74,471
  1. To request the World Bank to continue monitoring the implementation of CSM projects under phase I and to provide an update in its 2008 work programme; and
  2. To approve the 2007 work programme of the national phase-out of the production and consumption of CTC for process agent and other non-identified uses (phase I) on the understanding that the request for funding and support costs for the 2007 work programme would be submitted to the 51st Meeting together with a verification report on the implementation of the 2006 work programme.