The Executive Committee therefore decided:
- To take note of the verification report submitted by UNIDO on the 2007 carbon tetrachloride (CTC) production and consumption as process agent until August 2007;
- To approve the fourth tranche of funding of US $1,200,000 for the implementation of the 2008 annual programme of the Agreement on the Romania ODS production sector and US $90,000 as support costs to UNIDO, in view of the progress already achieved in establishing the CTC incinerator in Chimcomplex and the completion of the removal of the capability to produce CTC at Oltchim;
- To request UNIDO to withhold disbursement until it had verified completion of the 2007 work programme and had cleared with the Secretariat that the targets for 2007 had been achieved; and
- To request UNIDO to carry out the verification of the ODS production sector and the terminal phase-out of CTC for the process agent project in 2008 and 2009.