Following a discussion, the Executive Committee decided:
- To note:
- With appreciation, the status reports on projects with implementation delays submitted to the Secretariat by the Governments of Australia, Germany, Japan, and the four implementing agencies addressed in documents UNEP/OzL.Pro/ExCom/58/6 and UNEP/OzL.Pro/ExCom/58/6/Corr.1;
- The completion of one of the 19 projects listed with implementation delays and the removal of another project from the list of projects with implementation delays, owing to progress;
- That the Secretariat and the implementing agencies would continue monitoring those projects listed in Table 1 of Annex III to the present report as having had“some progress”, and report to the 59th Meeting;
- To request additional status reports on the projects listed in Table 2 of Annex III to the present report to be submitted to the 59th Meeting; and
- To cancel the following projects by mutual agreement of the implementing agencies and countries concerned:
| Agency | Code | Project title |
| Canada | BEN/PHA/49/PRP/15 | Project preparation for TPMP in Benin |
| Canada | TRI/FUM/49/TAS/19 | Technical assistance on MB in Trinidad and Tobago |
| UNIDO | IVC/ARS/46/INV/23 | Phase-out of CFC-12 in the manufacture of cosmetics aerosols by conversion to hydrocarbon aerosol propellant (HAP) at COPACI, Abidjan, Côte d’Ivoire |