The Executive Committee decided:
- To take note of the 2012 consolidated project completion report (PCR), including the schedule for submission of PCRs due and the lessons learned in Annex II to document UNEP/OzL.Pro/ExCom/68/7;
-
To request bilateral and implementing agencies concerned, by the end of January 2013:
- To establish full consistency of data reported in the PCRs in the inventory of approved projects database and in the annual progress reports, in cooperation with the Secretariat;
- To provide the information still missing in a number of PCRs;
- To clear the backlog of PCRs on projects completed before the end of 2006; and
- To invite all those involved in the preparation and implementation of projects to take into consideration the lessons learned from PCRs when preparing and implementing future projects.