Decision 79/21

July 2017
Project completion reports

Following the discussion, the Executive Committee decided:

  1. To note the 2017 consolidated project completion report (PCR) contained in document UNEP/OzL.Pro/ExCom/79/15;
  2. To urge bilateral and implementing agencies to submit to the 80th meeting PCRs for multi‑year agreements (MYAs) and individual projects that were due, and if they were not going to submit, to provide the reasons for not doing so and the schedule for submission;
  3. To urge lead and cooperating agencies to closely coordinate their work in finalizing their portions of PCRs to allow the lead implementing agency to submit the finished PCRs according on schedule;
  4. To urge bilateral and implementing agencies to enter clear, well written and thorough lessons learned when submitting their PCRs; and
  5. To invite all those involved in the preparation and implementation of MYAs and individual projects to take into consideration the lessons learned from PCRs, if relevant, when preparing and implementing future projects.