Decision 82/88

December 2018
China
World Bank
Production approvals and reports

The Executive Committee decided:

  1. To note the 2017–2018 progress report on the implementation of stage I of the HCFC production phase-out management plan (HPPMP) (stage I) for China considered by the Sub-group on the Production Sector;
  2. To note that the World Bank would submit a project completion report and return the remaining balances of stage I of the HPPMP at the 84th meeting;
  3. To note that US $13,076 of interest accrued in 2017 would be deducted from the first tranche of stage II of the HPPMP when approved;
  4. To note that the penalty of US $133,146, associated with the redirection of 887.64 metric tonnes of compensated HCFC production capacity towards feedstock production by the Changshu 3F Zhonghao New Chemical Material Co. Ltd; facility, would be included in the balances returned, at the 84th meeting, to the Multilateral Fund by the World Bank from stage I of the HPPMP in line with decision 80/79(d); and
  5. To request the Government of China through the World Bank to submit the final progress report of stage I of the HPPMP at the 83rd meeting.