Decision 84/27

December 2019
Projects with specific reporting requirements | HCFC phase-out management plans related

Following informal discussions among interested members, the Executive Committee decided to request the Secretariat taking into consideration discussions at the 84th meeting, to prepare, for the 85th meeting, a list of enterprises that had been funded under HCFC phase-out management plans for conversion to low global-warming-potential technologies, and that had experienced implementation delays due to issues related to availability in the local market and/or higher costs.