Decision 84/80

December 2019
Tunisia
FRA | UNEP | UNIDO
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note:
    1. The progress report on the implementation of the second tranche of stage I of the HCFC phase-out management plan (HPMP) for Tunisia;
    2. The Government’s commitment to place strict controls on the import of HCFC-141b for solvent applications;
  2. To request the Government of Tunisia, UNIDO, UNEP and the Government of France to submit progress reports on the implementation of the work programme associated with the final tranche on a yearly basis until the completion of the project, verification reports until approval of stage II of the HPMP and the project completion report to the 88th meeting; and
  3. To approve the third and final tranche of stage I of the HPMP for Tunisia, and the corresponding 2020 tranche implementation plan, in the amount of US $99,945, consisting of US $57,500, plus agency support costs of US $4,025 for UNIDO, US $15,000, plus agency support costs of US $1,950 for UNEP, and US $19,000, plus agency support costs of US $2,470 for the Government of France, on the understanding that no funds would be provided to end-users to replace equipment under the technical assistance.