The Executive Committee decided:
- To note the progress report of UNIDO as at 31 December 2020 contained in document UNEP/OzL.Pro/ExCom/88/16;
- To approve the extension of the completion dates of the projects listed below to allow for completion of the remaining ongoing activities, as reflected in Table 1 of document UNEP/OzL.Pro/ExCom/88/16:
- Enabling activities for HFC phase-down for Jordan (JOR/SEV/82/TAS/104), to 30 June 2022;
- Global chiller replacement project for Argentina (GLO/REF/80/DEM/344), to 31 December 2022;
- To approve the extension of the completion dates of the projects listed below to allow for completion of the remaining ongoing activities, as reflected in Table 3 of document UNEP/OzL.Pro/ExCom/88/16:
- Enabling activities for HFC phase-down for Chile (CHI/SEV/80/TAS/02+), to 30 June 2022;
- Enabling activities for HFC phase-down for Morocco (MOR/SEV/81/TAS/01+), to 31 December 2022;
- Enabling activities for HFC phase-down for Uruguay (URU/SEV/80/TAS/01+), to 30 June 2022; and
- To approve the recommendations related to ongoing projects with specific issues contained in Annex VI to the present report.