Decision in paragraph 107 in UNEP/OzL.Pro/ExCom/15/45

December 1994
Thailand
UNDP
Projects approved / deferred / transferred

Project proposals:  Thailand

107.     The Executive Committee approved the following projects to be implemented by UNDP and the funds indicated:

 

 

Approved amount

US $

Elimination of the use of CFC in the manufacture of flexible PUF cold cured mouldings, integral skin mouldings and rigid PUF articles at Thai Union

525,000

         Plus 13 per cent project support costs to UNDP

68,250

The Executive Committee requested UNDP to ensure that the old equipment replaced was disposed of in accordance with existing guidelines.

 

Elimination of the use of CFC in the manufacture of flexible PUF slabstock and cold cured mouldings at Somboon Paisarn

225,000

         Plus 13 per cent project support costs to UNDP

29,250

The Executive Committee requested UNDP to ensure that the old equipment replaced was disposed of in accordance with existing guidelines.

 

Elimination of the use of CFCs in the manufacture of flexible PUF slabstock at Karn Yang

170,000

        Plus 13 per cent project support costs to UNDP 

22,100

The Executive Committee requested UNDP to ensure that the old equipment replaced was disposed of in accordance wit.h existing guidelines