Decision 93/14

December 2023
Afghanistan | Dominica | Myanmar
UNEP | UNIDO
UNEP progress reports | Project cancellation

The Executive Committee decided

  1. To note the progress report of UNEP as at 31 December 2022 contained in document UNEP/OzL.Pro/ExCom/93/17
  2. To approve the extension, to 31 December 2024, of the completion date of stage I of the HCFC phase-out management plan (HPMP) for Dominica (first tranche (DMI/PHA/62/TAS/190) and second tranche (DMI/PHA/84/TAS/25)) to allow completion of the remaining ongoing activities, as reflected in table 5 of document UNEP/OzL.Pro/ExCom/93/17
  3. With regard to the HPMP for Afghanistan, to note: 
    1. The request from Afghanistan to transfer to UNIDO the following projects: stage I, fourth tranche (AFG/PHA/85/TAS/27); and stage II, first tranche (AFG/PHA/85/TAS/29); 
    2. That, at the 94th meeting, the remaining balances from the projects referred to in subparagraph (c)(i) above would be transferred from UNEP to UNIDO; 
    3. That UNIDO would submit the updated Agreements for stage I and stage II of the HPMP for Afghanistan, together with the revised implementation plans, to the 94th meeting; 
  4. To cancel the following projects of the HPMP for Myanmar and to request UNEP to return the remaining balances in line with decision 28/7: stage I, first tranche (MYA/PHA/68/TAS/14); stage I, second tranche (MYA/PHA/80/TAS/18); stage I, third tranche (MYA/PHA/86/TAS/23); preparation for stage II (MYA/PHA/83/PRP/21); and technical assistance for verification report (MYA/PHA/86/TAS/24); and 
  5. To approve the recommendations related to ongoing projects with specific issues contained in annex V to the present report.