73. The Executive Committee approved the amount of US$ 873,071 for the following amendments to the UNIDO work programme:
| India | Feasibility study for the recovery and recycling of CFC refrigerants | US$ 55,000 |
| Project formulation for phasing-out of ODSs in the unorganised sector | US$ 55,000 | |
| Project formulation for the conversion of electronic cleaning processes to non-CFC cleaning | US$ 74,000 | |
| Jordan | Preparation of investment proje cts for phasing-out CFCs in the refrigeration sector | US $90,000 |
| Egypt | Support for a National Coordination Unit for the Montreal Protocol-related activities | US$ 263,450 |
| Syria | Support to strengthen the General Commission for Environmental Affairs to implement Montreal Protocol-related activities | US $235,180 |
| Sub-total | US$ 772,630 | |
| Project Support Costs (13 per cent of sub-total) | US$ 100,441 | |
| Total | US$ 873,071 |