74. The Committee considered the recommendations of the Sub-Committee on Project Review and approved the following amendment to the 1994 UNIDO work programme for an amount of US $16,950, including US $1,950 as support costs for UNIDO:
| Country | Project | Approved amount |
| Egypt | Preparation of investment project on ODS phase-out for four additional refrigrator manufacturers in Egypt | 15,000 |
| Sub-total | 15,000 | |
| 13 per cent project support costs | 1,950 | |
| Total | 16,950 |