Decision 23/56

November 1997
Regime and operation including meeting dates and venues

The Executive Committee decided to adopt the following Calendar of Meetings and Work Programme of the Executive Committee for 1998 which took into consideration the projection of workload during 1998, the timing of other related important events such as the seventeenth OEWG meeting (6-10 July 1998) and the Tenth Meeting of the Parties (tentatively 17-27 November 1998):

* To be held back to back with the Tenth Meeting of the Parties in Cairo, Egypt.
Mtg No.TimingInterval from previous mtgWork to be done in the intervalAgenda
24th23-27 March 19984 monthsRevise 1998 business plans and work programmes. Complete the remaining projects from the 1997 business plans. Prepare policy papersApprove revised 1998 business plans and work programmes. Approve the remaining projects from 1997 business plans. Approve policy papers. Consider funding of projects for process agents
25th27-31 July 19984 monthsPrepare projects, policy papers, progress reports, evaluation of 1997 business plans, national status of phase-outApprove projects and policy papers. Review progress reports, evaluation of 1997 business plans and national status of phase-out
26th9-13 November 1998*4 monthsPrepare projects, policy papers, draft 1999 business plans, necessary elements of work programmesApprove projects, policy papers, draft 1999 business plans, necessary and non-contentious elements of work programmes