The Executive Committee noted the Sub-Committee’s decision to address, at its next meeting, the following additional reasons for delays in implementation:
(a) Changes in project specification by the beneficiary;
(b) Enterprises refrained from implementing their projects until their competitors’ projects had been approved or government regulations had been enacted;
(c) The bidding process resulted in higher costs;
(d) The difficulty of obtaining agreements on the transfer of technology;
(e) Prolonged contract negotiations;
(f) Changes in technology;
(g) Differences in appraised tonnage;
(h) Completion of grant agreements.