Decision 23/7

November 1997
Monitoring and evaluation - policies | Project completion reports | Guidelines for project submissions/presentation

The Executive Committee, having taken note of the Sub-Committee’s observations and recommendations (UNEP/OzL.Pro/ExCom/23/4/Add.1, paragraphs 6-13), decided:

(a) That utilized capacity should be deleted from the fifth bullet under baseline data as the other criteria would be sufficient to allow effective monitoring and evaluation;

(b) That a ninth bullet should be added to the milestones, as follows:

“the beginning of project activities at the country level as stated by the Article 5 Party concerned. Where possible, these activities should be listed.”;

(c) That the Monitoring and Evaluation Officer should be requested to report and provide advice in the future on the effectiveness of this additional milestone;

(d) That the Secretariat should propose milestones for non-investment projects for consideration at a future meeting;

(e) That the submission of project completion reports should be included as a milestone;

(f) That the standard components proposed in document UNEP/OzL.Pro/ExCom/23/6, as amended, should be included in investment project proposals as additional components.