Decision 27/59

March 1999
China | Indonesia | Jordan | Malaysia
Criteria for submission of project preparation proposals | Projects approved / deferred / transferred

Having considered the comments and recommendations of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/27/13, paras. 91-92), the Executive Committee decided:

(a) To approve the requests for project preparation for China, Indonesia, Jordan and Malaysia at the level of funding indicated in annex II to the present report [document UNEP/OzL.Pro/ExCom/27/48];

(b) That, following the intent of decision 23/51, when a project preparation request was submitted for a country, and the Executive Committee had already approved projects to phase out more than 80 per cent of the country’s baseline, the Implementing Agency should provide a clear delineation of remaining consumption in all sectors.