The Executive Committee, having considered the recommendation of the Sub-Committee on Monitoring, Evaluation and Finance (UNEP/OzL.Pro/ExCom/29/4, para.20) decided:
(a) To note with appreciation the reports on projects that have experienced implementation delays from the Governments of Australia, France and the United States of America and the four implementing agencies;
(b) To remove the projects that have experienced progress (as contained in Annex I to document UNEP/OzL.Pro/ExCom/29/7 and UNEP/OzL.Pro/ExCom/29/7/Corr.1) from the list of projects with implementation delays;
(c) To maintain the projects that have shown some progress (as contained in Annex II to document UNEP/OzL.Pro/ExCom/29/7 and UNEP/OzL.Pro/ExCom/29/7/Corr.1) for future reporting on projects with implementation delays, as appropriate;
(d) To note that the enterprise under the Hualing project (CPR/REF/22/INV/204), referred to in Decision 28/3 in connection with continued CFC use after project completion, has stopped using CFCs;
(e) To approve UNIDO’s request to cancel the Leulmi Foam project (ALG/FOA/22/INV/21) on the condition that any remaining funds should be returned and with the understanding that Leulmi Foam may not resubmit a request to the Multilateral Fund for any further support;
(f) To approve UNIDO’s request to transfer the equipment from the Leulmi Foam project to the Maghreb Mousse project (ALG/FOA/26/INV/29) on the condition that any remaining funds for this project (as a result of receiving equipment from the Leulmi Foam project) should be returned to the Multilateral Fund;
(g) To approve the cancellation of the Technofrig S.A. project of Romania (ROM/REF/19/INV/08) on the condition that any remaining funds for this project should be returned and with the understanding that Technofrig S.A. may submit a request for a different new project to the Multilateral Fund.