Decision 32/58

December 2000
Morocco
UNIDO
Projects approved / deferred / transferred

Morocco: Phase-out of methyl bromide for soil fumigation in strawberry production (UNIDO) (UNEP/OzL.Pro/ExCom/32/30/Morocco)

Having considered the recommendations of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/32/21, para. 78), the Executive Committee decided to approve the above project at the level of funding indicated in Annex VIII to the present report, in accordance with the agreement between the Government of Morocco and the Executive Committee contained in Annex XII to the present report,  on the understanding that:

(a) UNIDO would disburse the funds approved in tranches according to the proposed methyl bromide phase-out schedule indicated in the agreement contained in Annex XII;

(b) If Morocco did not meet the reduction requirements outlined in the agreement contained in Annex XII, UNIDO would withhold funding for the subsequent tranche until such time as the required reduction had been met;

(c) UNIDO would submit an annual progress report on the implementation of the project to the Fund Secretariat.

Related annexes
Annex VIII to document 32/44, projects and activities approved