Having considered the recommendation of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/33/17, para. 11), the Executive Committee decided that:
(a) Proposals to update refrigerant management plans should be in conformity with decision 31/48 and should be accompanied by:
(i) a progress report from implementing agencies on the status of work being undertaken in the projects approved as part of the refrigerant management plan; and
(ii) a written justification from countries for additional activities, explaining how the additional activities were related to the refrigerant management plan and the country’s phase-out commitments.
(b) The level of funding of such requests could be up to 50 per cent of the level of funding approved prior to the Thirty-first meeting for the preparation of the original refrigerant management plan;
(c) Approval of the additional funding would be contingent on submission of the progress reports and the written justification referred to above.