Having considered the comments and recommendations of the Sub-Committee on Monitoring, Evaluation and Finance (UNEP/OzL.Pro/ExCom/40/7, paragraphs 30 and 31), the Executive Committee decided:
- To take note of UNDP’s progress report contained in UNEP/OzL.Pro/ExCom/40/15 and UNEP/OzL.Pro/ExCom/40/15/Corr.1;
- To monitor the Garabouli foam project in the Libyan Arab Jamahiriya (LIB/FOA/32/INV/06) as a project with implementation delays and note its slow progress;
- To note that UNDP would report on up to 51 projects with implementation delays, including 29 projects that were so classified in 2002;
- Also to note that UNDP had 364 projects classified as completed for over one year with remaining balances totalling US $4,774,693; and
- To request UNDP to address the financial inconsistencies in the context of the reconciliation of accounts pursuant to Decision 38/9(d), noting that overruns should not be allowed pursuant to Decision 17/22.