Indonesia: Sector phase-out plan for elimination of CFCs in the refrigeration (MAC servicing) sector: 2004 annual programme (World Bank) (UNEP/OzL.Pro/ExCom/41/37)

Indonesia: Sector phase-out plan for elimination of CFCs in the refrigeration (manufacturing) sector (balance of second tranche) (UNDP) (UNEP/OzL.Pro/ExCom/41/37)

Indonesia: Sector phase-out plan for elimination of CFCs in the refrigeration (servicing) sector (second tranche) (UNDP) (UNEP/OzL.Pro/ExCom/41/37)

Having considered the recommendations of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/41/14, paragraph 128), the Executive Committee decided to approve:

  1. US $1,600,000 plus agency support costs of US $141,100 to UNDP for the refrigeration manufacturing sector plan (balance of second tranche);
  2. US $1,805,987 plus agency support costs of US $160,939 to UNDP for the refrigeration servicing sector plan (second tranche); and
  3. US $1,347,300 plus agency support costs of US $119,937 to the World Bank for the mobile air conditioning (MAC) sector (2004 annual programme).