Decision 41/76

December 2003
Türkiye
UNIDO
Projects approved / deferred / transferred

Having considered the comments and recommendations of the Sub-Committee on Project Review (UNEP/OzL.Pro/ExCom/41/14, paragraphs 144 and 145), the Executive Committee decided:

  1. To approve the terminal umbrella project for the solvent sector in Turkey at a total cost of US $531,644 plus agency support costs of US $39,873 for UNIDO;
  2. To stipulate that no further funding would be requested from the Multilateral Fund for the phase-out of CFC-113, TCA and CTC in Turkey; and
  3. Also to stipulate that, should the phase-out of bromochloromethane (BCM) in applicable process agent uses become eligible for funding, Turkey might submit a proposal for funding, consistent with the rules of the Multilateral Fund in effect at the time, for a level of consumption not exceeding 21.34 ODP tonnes of BCM.