Following a discussion, the Executive Committee decided:
- To approve in principle the terminal CFC phase-out management plan for Kenya at a total level of funding of US $725,000 plus agency support costs of US $94,250 for France;
- To approve the Agreement between the Government of Kenya and the Executive Committee contained in Annex XV to the present report;
- To approve funding of US $215,914 plus support costs of US $28,069 for France for the first tranche of the project; and
- That the disbursement of the first tranche would be contingent upon confirmation of the adoption of ODS regulations by the Government of Kenya to provide a legal basis for the existing licensing system and enable introduction of independent auditing and verification.