Following a discussion, the Executive Committee decided:
- To request the Secretariat to advise UNDP that the proposal to replace one enterprise in the terminal umbrella project approved for Paraguay (PAR/REF/34/INV/12) by three different enterprises could proceed, noting that the replacement resulted in a reduction in the total consumption of CFCs in the project of 1.75 ODP tonnes and in the return to the Multilateral Fund of US $23,945, including agency support costs, by UNDP, to be submitted to the 46th Meeting; and
- To authorize the Secretariat to agree to any future changes in terminal umbrella projects in cases where all cost and policy issues between the Secretariat and the implementing agency concerned had been resolved, and to report back to the Executive Committee.