Decision 45/43

April 2005
Romania
SWE | UNIDO
Projects approved / deferred / transferred

Following a discussion, the Executive Committee decided:

  1. To approve, in principle, the national CFC phase-out plan for Romania, at a total level of funding of US $545,300, plus agency support costs of US $47,470 for UNIDO and Sweden;
  2. To approve the agreement between the Government of Romania and the Executive Committee contained in Annex XII to the present report, and
  3. To approve the first tranche of the plan at a funding level of US $159,050, plus support costs of US $11,929 for UNIDO, and US $119,500, plus support costs of US $15,535 for Sweden.
Related annexes
Annex XII to document 45/55, ODS phase-out agreement with Romania