Decision 46/31

July 2005
Egypt
UNIDO
Projects approved / deferred / transferred

Following a discussion, the Executive Committee decided:

  1. To approve in principle the CFC phase-out plan for Egypt at a total level of funding of US $3,100,000 plus agency support costs of US $232,500 for UNIDO;
  2. To approve the draft agreement between the Government of Egypt and the Executive Committee contained in Annex VII to the present report; and
  3. To approve the funding for the first tranche of the phase-out plan at the amount of US $1,000,000, plus support costs of US $75,000 for UNIDO.
Related annexes
Annex VII to document 46/47, ODS phase-out agreement with Egypt