Decision 52/12

July 2007
Bosnia and Herzegovina | China | Guinea | Kuwait | Libya | Serbia
UNEP | UNIDO
UNIDO progress reports

Following a discussion on existing and proposed means of dealing with implementation delays, the Executive Committee decided:

  1. To note UNIDO’s progress report contained in document UNEP/OzL.Pro/ExCom/52/14;
  2. To define “implementation delays due to disbursement” as a level of disbursement below 1 per cent of the project budget 18 months after project approval;
  3. To request UNIDO to expedite the completion of the preparation of the metered- dose inhaler sector plan in China (CPR/ARS/44/PRP/422), the halon phase-out plan in Kuwait (KUW/HAL/45/PRP/07) and the carbon tetrachloride sector plan in Serbia (YUG/SOL/45/PRP/27);
  4. To take note of the information provided by Guinea, UNIDO and UNEP regarding the completion of the national survey, the work of the consultant and work on the terminal phase-out management plan;
  5. To request additional status reports on the following projects to be submitted to the 53rd Meeting:
    1. Halon phase-out project (BHE/HAL/42/TAS/18) and institutional strengthening project (BHE/SEV/43/INS/19) in Bosnia and Herzegovina;
    2. Halon phase-out project (LIB/HAL/47/TAS/26) and institutional strengthening project (LIB/SEV/32/INS/04) in the Libyan Arab Jamahiriya; and
  6. To note that UNIDO would report to the 53rd Meeting on up to 15 projects with implementation delays in 2006, including seven projects that were so classified in 2005.