Decision 52/23

July 2007
Bhutan | Comoros | Costa Rica | Gabon | Kuwait | Madagascar | Nepal | Oman | Republic of Moldova | Saint Lucia | Senegal
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To approve the projects and activities submitted for blanket approval at the level of funding indicated in Annex II to the present report, together with the conditions or provisos included in the corresponding project evaluation sheets and those conditions attached to projects by the Executive Committee;
  2. To approve the agreement between the Government of Bhutan and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex III to the present report at a total amount of US $75,000 plus agency support costs for the project at the amount indicated in Annex II;
  3. To approve the agreement between the Government of Comoros and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex IV to the present report at a total amount in principle of US $205,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  4. To approve the agreement between the Government of Costa Rica and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex V to the present report at a total amount in principle of US $565,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  5. To approve the agreement between the Government of Gabon and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex VI to the present report at a total amount in principle of US $205,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  6. To approve the agreement between the Government of Kuwait and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex VII to the present report at a total amount in principle of US $565,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  7. To approve the agreement between the Government of Madagascar and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex VIII to the present report at a total amount in principle of US $345,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  8. To approve the agreement between the Government of Moldova and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex IX to the present report at a total amount in principle of US $520,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  9. To approve the agreement between the Government of Nepal and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex X to the present report at a total amount in principle of US $170,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  10. To approve the agreement between the Government of Oman and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex XI to the present report at a total amount in principle of US $470,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  11. To approve the agreement between the Government of Saint Lucia and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex XII to the present report at a total amount in principle of US $205,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II;
  12. To approve the agreement between the Government of Senegal and the Executive Committee of the Multilateral Fund for the terminal phase-out management plan contained in Annex XIII to the present report at a total amount in principle of US $565,000 plus agency support costs and the first tranche for the project at the amount indicated in Annex II; and
  13. That for projects relating to the renewal of institutional strengthening, blanket approval included approval of the observations to be communicated to recipient governments contained in Annex XIV to the present report.
Related annexes
Annex V to document 52/55, ODSs phase-out agreement with Costa Rica