The Executive Committee decided:
- To amend the maximum allowable amount of CTC used in process agent applications listed in the interim table A-bis of decision XVII/8 of the Seventeenth Meeting of the Parties, and in potential future process agent applications as identified and reported by the Government of China, from the 14,300 ODP tonnes currently included in the Agreement on Phase II of the sector plan to 6,600 ODP tonnes in 2008 and 2009;
- To approve the 2008 annual work programme for Phase II of the sector plan for phasing out CTC production and consumption for process agents at US $10 million, and the associated support costs of US $750,000, with the understanding that the request for funding and support costs would be submitted by the World Bank to the 55th Meeting, together with a verification report on the implementation of the 2007 annual programme.