Decision 54/26

April 2008
Pakistan
UNDP
Projects approved / deferred / transferred

Following a discussion, the Executive Committee decided:

  1. To approve the request for project preparation for a metered-dose inhaler (MDI) project in Pakistan at the funding level of US $60,000 plus agency support costs of US $4,500 for UNDP and to confirm that the information provided was consistent with the requirements of decision 51/34;
  2. To request UNDP to note the following:
    1. Project preparation should cover only the enterprise and consumption identified at the time when the remaining eligible CFC consumption had been agreed on, and target only the percentage that was locally owned; and
    2. Any new MDI production after the 42nd Meeting, at which the last sector plan for Pakistan had been approved, was not eligible for funding consistent with approvals made for similar investment projects in that sector.