Decision 55/9

July 2008
Argentina | Bosnia and Herzegovina | Democratic People's Republic of Korea | Honduras | Kuwait | Kyrgyzstan | Libya | North Macedonia | Qatar | Romania | Serbia | Syrian Arab Republic
UNIDO
UNIDO progress reports | Implementation delays and status reports

Following the presentation, the Executive Committee decided:

  1. To note UNIDO’s progress report as contained in document UNEP/OzL.Pro/ExCom/55/13;
  2. To request that additional status reports on the following projects be submitted to the 56th Meeting:
    1. National methyl bromide phase-out plan in Honduras (HON/FUM/50/INV/21);
    2. National methyl bromide phase-out plan in the Libyan Arab Jamahiriya (LIB/FUM/47/INV/27);
    3. CFC phase-out plan in Romania (ROM/PHA/45/INV/30 and ROM/PHA/48/INV/34);
    4. CFC phase-out plan in Serbia (YUG/PHA/43/TAS/23);
    5. CFC phase-out plan in the Syrian Arab Republic (SYR/PHA/49/INV/96);
    6. CTC phase-out plan in the Democratic People's Republic of Korea (DRK/PHA/41/INV/30);
    7. Institutional strengthening in Bosnia and Herzegovina (BHE/SEV/43/INS/19);
    8. Institutional strengthening in Qatar (QAT/SEV/49/INS/08);
    9. Institutional strengthening in Serbia (YUG/SEV/44/INS/25);
    10. Methyl bromide phase-out project in Argentina (ARG/FUM/30/INV/105);
    11. Halon phase-out plan preparation in Kuwait (KUW/HAL/45/PRP/07);
    12. Phase-out plan in the CTC sector in Serbia (YUG/SOL/45/PRP/27);
    13. Halon banking project in Bosnia and Herzegovina (BHE/HAL/42/TAS/18);
    14. Halon banking project in Kyrgyzstan (KYR/HAL/48/TAS/12);
    15. Halon banking project in the Libyan Arab Jamahiriya (LIB/HAL/47/TAS/26);
  3. To note that UNIDO would report to the 56th Meeting on up to 12 projects with implementation delays in 2007 contained in Annex III to the present report, including five projects that had been classified as such in 2006;
  4. To note that the equipment from the cancelled project in the Former Yugoslav Republic of Macedonia at Alkaloid A.D. (MDN/ARS/32/INV/17) would be donated to a university in that country, as all attempts to redeploy it to other countries had been unsuccessful; and
  5. To request UNIDO to expedite completion of the preparation of the halon phase-out plan in Kuwait (KUW/HAL/45/PRP/07) and the CTC sector plan in Serbia (YUG/SOL/45/PRP/27).
Related annexes
Annex III to document 55/59, projects with implementation delays