Decision 56/6

November 2008
UNEP
Institutional strengthening | Desk studies and evaluations

The Executive Committee decided:

  1. To take note of the final report on the evaluation of institutional strengthening projects as presented in document UNEP/OzL.Pro/ExCom/56/8;
  2. To request:
    1. The Fund Secretariat to take into account the findings of the evaluation in its review of the funding for institutional strengthening pursuant to Executive Committee decision 53/39;
    2. The implementing agencies to review procedures for fund disbursement and reporting and administrative requirements with a view to minimizing project implementation delays for institutional strengthening projects while ensuring that accountability for institutional strengthening funds disbursed was maintained;
    3. The Fund Secretariat, implementing agencies and the bilateral agencies, in consultation with Article 5 countries, to agree on a set of objectives, expected results and indicators, which would be incorporated into future institutional strengthening extension requests;
    4. The implementing agencies to monitor implementation of institutional strengthening projects and to submit any requests for renewal up to six months in advance of expiry of the existing project in line with Executive Committee decision 19/29;
    5. The Fund Secretariat to review the formats for terminal reports and extension requests for institutional strengthening projects with the aim of rationalizing reporting and project review;
    6. UNEP, through the Compliance Assistance Programme (CAP), to allocate time during network meetings to discuss institutional strengthening reporting and the importance of requesting renewals on time; and
    7. UNEP to develop a training module on policy and technical issues related to the reduction of HCFCs, with technical inputs from the other implementing agencies, for briefings of national ozone units during network meetings.