Decision 57/13

April 2009
Costa Rica | Côte d'Ivoire | Dominican Republic | India | Maldives
CAN | FRA | DEU | ITA | UNDP | UNEP | UNIDO | World Bank
Tranche submission delays

Following the discussions, the Executive Committee decided:

  1. To note the information on annual tranches of multi-year agreements (MYAs) submitted to the Secretariat by Canada, France, Germany, Italy, UNDP, UNEP, UNIDO, and the World Bank as contained in the document on annual tranche submission delays (UNEP/OzL.Pro/ExCom/57/14);
  2. To note that 58 of the 90 annual tranches of MYAs due for submission had been submitted on time to the 57th Meeting;
  3. That letters should be sent to the relevant implementing agencies and applicable Article 5 countries regarding the annual tranches that had not been submitted to two or more consecutive Meetings, as indicated in Table 1 in Annex VIII to the present report, with the reasons stated for the delay, and to encourage implementing agencies and the relevant Article 5 Governments to take actions to expedite the implementation of the approved tranches so that tranches due for submission could be presented to the 58th Meeting, provided that sufficient progress had been made;
  4. That letters should be sent to the relevant bilateral and implementing agencies and applicable Article 5 countries regarding the annual tranches that had been due for submission to the 57th Meeting, as indicated in Table 2 in Annex VIII to the present report, with the reasons stated for the delay, and to encourage bilateral and implementing agencies and the relevant Article 5 Governments to take actions to expedite the implementation of the approved tranches so that tranches due for submission could be presented to the 58th Meeting, provided that sufficient progress had been made; and
  5. To encourage:
    1. The Government of India to submit its CFC production sector requests to the 58th Meeting;
    2. The Government of Costa Rica to expedite the implementation of the existing tranches of its methyl bromide phase-out plan, in order to submit the next tranche for approval as soon as possible;
    3. The Governments of Côte d’Ivoire and the Maldives to expedite the implementation of their terminal phase-out management plans in order to submit the 2009 annual tranches for review as soon as possible;
    4. The Government of the Dominican Republic to submit a complete verification report of its national phase-out plan to the 58th Meeting.
Related annexes
Annex VIII to document 57/69, annual tranches not submitted