Decision 57/24

April 2009
China
World Bank
Projects approved / deferred / transferred

Following the discussion, the Executive Committee decided:

  1. To approve the requests for project preparation for three demonstration projects in China in line with decision 55/43(e) and decision 56/16(i), at the amounts indicated below:
    1. Preparation of a demonstration project for phase-out of HCFC in spray foam: US $30,000, plus agency support costs of US $2,250 for the World Bank;
    2. Preparation of a demonstration project for phase-out of HCFC in foam insulation for water heaters: US $30,000, plus agency support costs of US $2,250 for the World Bank; and
    3. Preparation of demonstration project for phase-out of HCFC for foam system house: US $80,000, plus agency support costs of US $6,000 for the World Bank.