Decision 57/8

April 2009
Egypt | Thailand
UNDP
UNDP business plans | Performance indicators

The Executive Committee decided:

  1. To endorse the planned activities for 2009 in UNDP’s 2009-2011 business plan as contained in document UNEP/OzL.Pro/ExCom/57/9, and subject to the considerations contained in sub-paragraph (c) below, while noting that endorsement denoted neither approval of projects identified therein nor their funding levels;
  2. To note the planned activities for 2010 and 2011 in UNDP’s 2009-2011 business plan as contained in document UNEP/OzL.Pro/ExCom/57/9, and subject to the considerations contained in sub-paragraph (c) below;
  3. With regard to the 2009-2011 business plan as a whole:
    1. To note sub-paragraph (f) in decision 57/6 with regard to metered-dose inhaler transition strategies, HCFC foam demonstration projects, HCFC refrigeration demonstration projects, HCFC solvent demonstration projects, and ODS disposal activities;
    2. To note the removal by UNDP of the following ODS disposal activities:
  4. To include the following projects:
CountryProjectTotal value in 2009 (US $)Total value in 2010 (US $)Total value in 2011 (US $)Total value after 2011 (US $)Total ODS (ODP tonnes)
ThailandProject preparation for air- conditioning sectors, Excluding air-to-air conditioning118,0000000
ThailandAir conditioning sector plan05,000,0005,000,00010,000,000200
  1. To approve the performance indicators for UNDP as contained in Annex IV to the present report.
Related annexes
Annex IV to document 57/69, 2009 UNDP performance indicators