Following a discussion, the Executive Committee decided:

  1. To note the World Bank’s progress report contained in document UNEP/OzL.Pro/ExCom/58/15;
  2. To request that additional status reports on the following projects be submitted to the 59th Meeting:
    1. National CFC phase-out management plan in Antigua and Barbuda (ANT/PHA/44/INV/10);
    2. The chiller component of the national CFC phase-out plan in Argentina (ARG/PHA/47/INV/148);
    3. National ODS phase-out plan in Tunisia (TUN/PHA/49/INV/47);
    4. HCFC phase-out management plan preparation activities in China (CPR/PHA/55/PRP/467 and CPR/PHA/55/PRP/468), Ecuador (ECU/PHA/55/PRP/40), Philippines (PHI/PHA/55/PRP/84), Thailand (THA/PHA/55/PRP/151) and Viet Nam (VIE/PHA/55/PRP/50);
    5. Argentina methyl bromide demonstration project (ARG/FUM/29/DEM/93);
    6. Global chiller project (GLO/REF/47/DEM/268); and
  3. To note that the World Bank would report to the 59th Meeting on three projects with implementation delays contained in Table 1 of Annex V to the present report, all of which had been classified as such in 2007.
Related annexes
Annex V to document 58/53, projects with implementation delays, IS projects with no funds disbursed, and IS projects with additional detail requested