Following the presentation, the Executive Committee decided:
- To note UNDP’s progress report contained in document UNEP/OzL.Pro/ExCom/61/15;
- request the submission to the 62nd Meeting of the Executive Committee of additional status reports for the projects listed in Annex VIII to the present report;
- To report on the additional work identified, based on the stakeholder workshop to be held in July 2010, for the methyl formate foam demonstration project in Mexico (MEX/FOA/56/DEM/141);
- To request UNDP to integrate the RMP activities in Barbados (BAR/REF/43/TAS/11 and BAR/REF/43/TAS/12) into the country’s HPMP in the light of decision 60/11(b); and
- To note that UNDP would report to the 62nd Meeting on up to nine projects with implementation delays in 2009, including five projects that had been classified as such in 2008.