Decision 63/45

April 2011
Mauritius
DEU
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To approve, in principle, the HCFC phase-out management plan (HPMP) for Mauritius for the period 2011 to 2030, at the amount of US $1,000,000, plus agency support costs of US $120,000 for the Government of Germany, on the understanding that this would be the total funding available from the Multilateral Fund to achieve the complete phase-out of HCFCs by 1 January 2030;
  2. To note that the Government of Mauritius had agreed to establish an estimated baseline of 10.2 ODP tonnes as its starting point for sustained aggregate reduction in HCFC consumption, calculated using consumption of 9.7 ODP tonnes for 2009 which excluded 1.0 ODP tonne in stockpiles and consumption of 10.6 ODP tonnes estimated for 2010;
  3. To approve the draft Agreement between the Government of Mauritius and the Executive Committee for the phase-out of HCFCs, as contained in Annex XXVII to the present report;
  4. To request the Fund Secretariat, once the baseline data were known, to update Appendix 2-A to the Agreement to include the figures for maximum allowable consumption, and to notify the Executive Committee of the resulting change in the levels of maximum allowable consumption and of any potential related impact on the eligible funding level, with any adjustments needed being made when the next tranche was submitted; and
  5. To approve the first tranche of the HPMP for Mauritius, and the corresponding implementation plan, at the amount of US $157,050, plus agency support costs of US $18,846 for the Government of Germany.
Related annexes
Annex XXVII to docucment 63/60, HPMP stage I agreement with Mauritius