Decision 64/3

July 2011
India
World Bank
Consolidated business plans | Tranche submission delays

The Executive Committee decided:

  1. To note:
    1. The report on the status of the 2011 business plans as contained in documents UNEP/OzL.Pro/ExCom/64/5 and UNEP/OzL.Pro/ExCom/64/5/Add.1, and the fact that US $64.9 million in activities in plans required for compliance had not been submitted to the 64th meeting;
    2. The information on annual tranche submission delays under multi-year agreements (MYAs) submitted to the Secretariat by the World Bank as contained in document UNEP/OzL.Pro/ExCom/64/5;
    3. That three out of four annual tranches of MYAs due for submission had been submitted on time to the 64th meeting; and
  2. To request the World Bank to work with the Government of India to expedite the signing of the agreements for the accelerated CFC production sector closure project (IND/PRO/59/INV/435) as soon as possible to enable the second tranche of the agreement to be submitted to the 65th meeting.