The Executive Committee decided:
- To approve, in principle, the solvent sector plan under stage I of the HCFC phase-out management plan (HPMP) for China for the period 2011 to 2015, at the amount of US $5,000,000, plus agency support costs for UNDP;
- To deduct 65.9 ODP tonnes of HCFCs from the starting point for sustained aggregate reduction in HCFC consumption;
- To approve the draft Agreement between the Government of China and the Executive Committee for the reduction in consumption of HCFCs, as contained in Annex XXII to the present report, to replace the previous Agreement approved at the 64th meeting by decision 64/49;
- To request the Fund Secretariat, once the baseline data were known, to update the Agreement, including Appendix 2-A, with the figures for maximum allowable consumption, and to notify the Executive Committee of the resulting change in the levels of maximum allowable consumption accordingly; and
- To approve the first tranche of the solvent sector plan under stage I of the HPMP for China and the corresponding implementation plan for 2011-2012 at the amount of US $2,500,000, plus agency support costs of US $187,500 for UNDP.