Decision 66/4

April 2012
Croatia
FRA | ISR | ITA | JPN | POR | ESP | UNEP | UNIDO
Country programme data and prospect for compliance | Implementation delays and status reports | Project cancellation

Following the discussion, the Executive Committee decided:

  1. To note:
    1. With appreciation, the status reports and reports on projects with implementation delays submitted to the Secretariat by the implementing agencies and the Governments of France, Italy, Japan and Portugal addressed in document UNEP/OzL.Pro/ExCom/66/6;
    2. That 59 country programme implementation reports for the year 2010 had been submitted through the web-based system, which had been initiated on 25 April 2007;
    3. The completion of seven of the 22 projects listed with implementation delays, as indicated in Annex III to document UNEP/OzL.Pro/ExCom/66/6 and as updated at the meeting;
    4. That the Secretariat and the implementing agencies would take established actions according to the Secretariat’s assessments (some progress as per Annex IV to document UNEP/OzL.Pro/ExCom/66/6) and report to and notify governments and implementing agencies as required;
  2. To request:
    1. That a letter of possible cancellation be sent in respect of the project Global technical assistance programme in the chiller sector (GLO/REF/48/TAS/275) implemented by UNEP;
    2. Additional status reports on the projects listed in Annexes II and III to the present report;
    3. The Governments of Israel and Spain to provide their report on projects with implementation delays to the 67th meeting of the Executive Committee; and
    4. The cancellation by mutual agreement of the project Phase-out of HCFC-141b from the manufacturing of polyurethane rigid foam at Pavusin (CRO/FOA/59/INV/34) implemented by UNIDO.
Related annexes
Annex III to document 66/54, projects with additional status reports requests for HPMP development