Decision 68/21

December 2012
Brazil
DEU | UNDP
Projects approved / deferred / transferred

The Executive Committee decided:

  1. To note the progress report on the implementation of the first tranche of stage I of the HCFC phase-out management plan (HPMP) for Brazil; and
  2. To approve the second tranche of stage I of the HPMP for Brazil, and the corresponding tranche implementation plans, at the amount of US $6,389,727, consisting of US $3,400,000, plus agency support costs of US $255,000 for UNDP, and US $2,472,727, plus agency support costs of US $262,000 for the Government of Germany.