Decision 71/24

December 2013
Project completion reports

The Executive Committee decided:

  1. To take note of the 2013 consolidated Project Completion Report (PCR) contained in document UNEP/OzL.Pro/ExCom/71/13, including the schedule for submission of PCRs due and the lessons learned;
  2. To request the bilateral and implementing agencies concerned:
    1. To establish by the end of January 2014, in cooperation with the Secretariat, full consistency of data reported in the PCRs in the Inventory of approved projects and in the annual progress reports;
    2. To provide to the Secretariat by the end of January 2014 the information still missing in a number of PCRs;
    3. To clear by the end of January 2014 the backlog of PCRs on projects completed before the end of 2006; and
  3. To invite all those involved in the preparation and implementation of projects to take into consideration the lessons learned from PCRs when preparing and implementing future projects.