The Executive Committee decided:
- To note:
- The status reports and compliance contained in documents UNEP/OzL.Pro/ExCom/71/6 and UNEP/OzL.Pro/ExCom/71/6/Corr.1;
- That 80 of the 122 countries that had provided 2012 data had submitted their country programme (CP) implementation reports through the web-based system;
- That the Secretariat and the implementing agencies would take established actions according to the Secretariat’s assessments and report on implementation delays, notifying governments and implementing agencies as required;
- To request:
- UNEP to report on the status of the establishment of Botswana’s and South Sudan’s licensing systems by the 72nd meeting;
- The Governments of Israel and Spain to provide their implementation delay reports to the 72nd meeting;
- The submission of additional status reports to the 72nd meeting on the projects listed in Annex III to the present report, as well as the HCFC phase-out management plan development for Mauritania (MAU/PHA/55/PRP/20) under UNEP implementation;
- The Secretariat to send letters of possible cancellation in respect of the following projects:
| Agency | Code | Project title |
| UNIDO | LEB/DES/61/PRP/72 | Preparation for pilot demonstration project on ODS waste management and disposal |
| UNIDO | MOZ/FUM/60/TAS/20 | Technical assistance for the elimination of controlled uses of methyl bromide in soil fumigation |
| UNIDO | TUN/FOA/58/PRP/50 | Preparation for HCFC phase-out investment activities (polyurethane foam sector) |
| UNIDO | TUN/PHA/55/PRP/48 | Preparation of an HCFC phase-out management plan |
- To reinstate at the 71st meeting, the following project preparation activities for Costa Rica, Cuba and Paraguay that had been closed as per decision 70/7(b)(iii):
| Country | Agency | Code | Project title |
| Costa Rica | UNDP | COS/PHA/55/PRP/39 | Preparation of an HCFC phase-out management plan |
| Costa Rica | UNDP | COS/REF/57/PRP/41 | Preparation for HCFC phase-out investment activities (refrigeration manufacturing sector) |
| Cuba | UNDP | CUB/FOA/57/PRP/41 | Preparation for HCFC phase-out investment activities (foam sector) |
| Cuba | UNDP | CUB/PHA/56/PRP/40 | Preparation of an HCFC phase-out management plan |
| Cuba | UNDP | CUB/REF/58/PRP/42 | Preparation for HCFC phase-out investment activities (manufacturing sector) |
| Paraguay | UNDP | PAR/FOA/57/PRP/21 | Preparation for HCFC phase-out investment activities (foam sector) |
| Paraguay | UNDP | PAR/PHA/57/PRP/22 | Preparation of an HCFC phase-out management plan (additional funding) |