The Executive Committee decided:
- To note:
- The progress report on the implementation of the first tranche of the HCFC phase-out management plan (HPMP) for Mauritius;
- That the Secretariat had updated paragraph 1, Appendices 1-A and 2-A of the Agreement between the Government of Mauritius and the Executive Committee, based on the established HCFC baseline for compliance and the revised funding level, and that a new paragraph 16 had been added to indicate that the updated Agreement* superseded that reached at the 63rd meeting, as contained in Annex XII to the present report;
- That the revised starting point for sustained aggregate reduction in HCFC consumption was 8.0 ODP tonnes, calculated using actual consumption of 10.7 ODP tonnes and 5.3 ODP tonnes reported for 2009 and 2010, respectively, under Article 7 of the Montreal Protocol and that the revised funding level for the HPMP for Mauritius was US $950,000, plus agency support costs, in accordance with decisions 60/44(f)(xii) and 62/10; and
- To approve the second tranche of the HPMP for Mauritius, and the corresponding 2014‑2017 tranche implementation plan, in the amount of US $131,400, plus agency support costs of US $15,851 for the Government of Germany.
*This Agreement was revised as per Decision 93/36.